A portion of Marina Park will be closed for drilling equipment and pipeline construction. The drilling equipment will be enclosed in a 24-foot sound wall perimeter for potential noise mitigation. In addition, a portion of the parking lot will be closed for contractor staging, pipe storage, and assembly.

Access to the walking paths will be maintained as well as access to the Leo Robbins Sailing Center. 

After construction is completed, the park will be restored to its pre-construction condition. Expected completion date is by Memorial Day 2024.