When will construction of the outfall take place?

The ocean outfall and pipeline installation is expected to take approximately 11 months to complete. The project has two (2) segments: 

  1. Offshore segment: There will be two (2) horizontal directional drill locations. One at Marina Park and one near the Ventura Port District across the Harbor. Work at Marina Park is expected to be completed by May 2024. 
  2. Onshore segment: The pipeline installation will be within Anchors Way, Schooner Drive, and Harbor Boulevard to the existing Ventura Water Reclamation Facility. This work is expected to be completed by July 2024.