Project Description
This project consists of resurfacing Johnson Drive from Telephone Road to Bristol Road; and includes cold milling, pavement repairs, asphalt overlay, manhole and valve adjustments to grade, installing street name signs, striping, and replacement of traffic inductive loops. Landscape and beautification opportunities will be considered as part of this project.
Project Status
In Construction
UPCOMING WORK SCHEDULE
- Telephone Road to Ralston Street - week of February 8, 2021
- Ralston Street to Bristol Road - week of February 22, 2021
- Bristol Road to Telephone Road - week of March 1, 2021
Estimated Schedule
January 2021 - April 2021
Contractor
Toro Enterprises
City Contacts
Zach Bryant, Assistant Construction Manager
Email
Chuck Thrall, Senior Construction Inspector
Email
Click here to view the Adopted Capital Improvement Plan for 2020-2026