Project Description
Replacement of two boilers, the three heat exchangers, digester gas mixing system on top of the digesters, and hot water recirculation system inside digester equipment building. Includes electrical and instrumentation improvements, and replacement of gas flare system. Replaces gas mixing system with a chopper/mixing pump with nozzles. Water jackets inside the tank will be replaced with heat exchangers external to the tanks requiring sludge circulation pumps. Install davit crane and rail system for equipment removal and maintenance.
Project Status
In Construction
Estimated Schedule
September 2019 - November 2020
Contractor
Cushman
City Contacts
Zach Bryant, Assistant Construction Manager
Email
Robert Payer, Senior Construction Inspector
Email
Click here to view the Adopted Capital Improvement Plan for 2020-2026