Posted on: October 21, 2020

Wastewater Plant - Digester Improvement

Project Description

Replacement of two boilers, the three heat exchangers, digester gas mixing system on top of the digesters, and hot water recirculation system inside digester equipment building. Includes electrical and instrumentation improvements, and replacement of gas flare system. Replaces gas mixing system with a chopper/mixing pump with nozzles. Water jackets inside the tank will be replaced with heat exchangers external to the tanks requiring sludge circulation pumps. Install davit crane and rail system for equipment removal and maintenance.

Project Status 

In Construction 

Estimated Schedule

September 2019 - November 2020 

Contractor

Cushman

City Contacts

Zach Bryant, Assistant Construction Manager
Email 

Robert Payer, Senior Construction Inspector
Email  

Click here to view the Adopted Capital Improvement Plan for 2020-2026





Facebook Twitter Email

Other News in Public Work Projects

Oxnard Plain Aquifer Monitoring Well

Posted on: April 8, 2021

Wastewater Plant Aeration Blowers

Posted on: April 8, 2021

Pierpont Stormwater Lift Stations

Posted on: January 28, 2021
MeasureO

Midtown Commons Parking Lot Improvements

Posted on: December 1, 2020

Sewerline Replacement - Eastman Ave

Posted on: October 21, 2020

Mound Well 2 - Phase II

Posted on: October 21, 2020

Wastewater Plant - Aeration Blowers

Posted on: October 21, 2020

Emergency Generators - Various Sites

Posted on: October 21, 2020

HWY 126 Bike Path Closure

Posted on: October 21, 2020

Mound Well 2 - Phase I

Posted on: October 21, 2020

Mound Well 3 - Phase III

Posted on: October 21, 2020
SB1-Logo

Telephone Road Resurfacing

Posted on: October 21, 2020