Project Description

FUNDED BY MEASURE O. This project is to repair existing sidewalks and install/upgrade ADA access ramps from Victoria Avenue to the eastern boundary at over 100 locations. The improvements include the installation of 104 curb ramps, retrofitting 52 curb ramps with a tactile surface, and 5,000 square feet of sidewalk and driveway repair. 

Project Status 

In Construction 

Estimated Schedule

August 2020 - October 2020 