Project Description
The project includes pumps and motors replacement and construction of a new motor control center (MCC) in a new location as the current location was damaged by a motorist. Completion of this project will provide a more reliable pump station that feeds water to the higher pressure zone north of Poli Street.
Project Status
In Construction
Estimated Schedule
January 2020 - January 2021
Contractor
Central Coast Engineering
City Contacts
Zach Bryant, Assistant Construction Manager
Email
Robert Payer, Senior Construction Inspector
Email
Click here to view the Adopted Capital Improvement Plan for 2020-2026