Public Work Projects

Posted on: October 21, 2020

Seaward - Poli Booster Pump Station Upgrade

Project Description

The project includes pumps and motors replacement and construction of a new motor control center (MCC) in a new location as the current location was damaged by a motorist. Completion of this project will provide a more reliable pump station that feeds water to the higher pressure zone north of Poli Street.

Project Status 

In Construction 

Estimated Schedule

January 2020 - January 2021

Contractor

Central Coast Engineering 

City Contacts

Zach Bryant, Assistant Construction Manager
Email 

Robert Payer, Senior Construction Inspector
Email  

Click here to view the Adopted Capital Improvement Plan for 2020-2026





Facebook Twitter Email

Other News in Public Work Projects

Pierpont Stormwater Lift Stations

Posted on: January 28, 2021
MeasureO

Midtown Commons Parking Lot Improvements

Posted on: December 1, 2020

Sewerline Replacement - Eastman Ave

Posted on: October 21, 2020

Mound Well 2 - Phase II

Posted on: October 21, 2020

Wastewater Plant - Aeration Blowers

Posted on: October 21, 2020

Emergency Generators - Various Sites

Posted on: October 21, 2020

HWY 126 Bike Path Closure

Posted on: October 21, 2020

Mound Well 2 - Phase I

Posted on: October 21, 2020
cip91052

Johnson Drive Resurfacing

Posted on: October 21, 2020

Mound Well 3 - Phase III

Posted on: October 21, 2020

Wastewater Plant - Digester Improvement

Posted on: October 21, 2020

Walker Street Resurfacing

Posted on: October 21, 2020
SB1-Logo

Ralston and Victoria Street Resurfacing

Posted on: October 21, 2020
MeasureO

Eastside Sidewalk ADA Improvements

Posted on: October 21, 2020
SB1-Logo

Telephone Road Resurfacing

Posted on: October 21, 2020